maxLevel1

Description of the order

Introduction

The Order Response Status (hereinafter called Order Response) is sent from a Seller to a Buyer, to inform the Buyer about the latest status of the related purchase order.

Process

The Order Response is submitted by the Seller to Onetrail

TPN™

TPN. Onetrail

TPN™

TPN processes the Order Response and submits it to the Buyer in their requested format.

Process management

The time between Orders and Order Status (Update) varies per Seller and depends on when the Order Status (Update) Messages are delivered to Onetrail by the Seller.


Info

For more detailed information examples about the supported order response processes scenarios we refer to: order response processesexamples


Order Status scenarios

Onetrail TPN™ TPN supports the following Order Status scenarios (or combinations):

  1. Scenario 1: Order Confirmed without changes;
  2. Scenario 2: Order Confirmed with changes;
  3. Scenario 3: Order on-hold;
  4. Scenario 4: Order-line on-hold;
  5. Scenario 5: Order Deleted;
  6. Scenario 6: Order Line(s) Deleted;
  7. Scenario 7: Order-line is added;
  8. Scenario 8: Order-line is split;

Info

For information on the scenarios are detailed in the Syntax paragraph.

Content

The Global Location Numbers (formerly known as EAN address codes) is used to refer to companies and addresses in order messages. These codes can be supplied by Onetrail unless a Trading Partner already has GLNs. The following GLNs are relevant to the Order Response Message (OrdRsp):

UBL XML:

  • To identify the Seller: fromRoleSellerSupplierParty
  • To identify the Buyer: toRoleBuyerCustomerParty
  • Where the goods are shipped to in case of warehouse shipment: ShipTo

The planned shipment date is supported by Onetrail in the OrdRsp messages. The planned shipment date can be "provided" and / or "calculated" in the OrdRsp.

The provided shipment date is mandatory, while the calculated shipment date is optional in the OrdRsp Message.

Several scheduledEvents are supported by Onetrail as documented in ORDRSP 3.1.. The GlobalTransportationEventCode is Ship. Ship is a fixed value as dispayed in the image below. The following options are supported:

  • Ship
  • Ship Calculated (optional)
  • Delivery (optional)
  • Delivery Calculated (optional)

<tns:scheduledEvent>
<tns:TransportationEvent>
<tns:DateStamp>20140307T000000</tns:DateStamp>
<tns:GlobalTransportEventCode>Ship</tns:GlobalTransportEventCode>
</tns:TransportationEvent>
</tns:scheduledEvent>
<tns:scheduledEvent>
<tns:TransportationEvent>
<tns:DateStamp>201403010T000000</tns:DateStamp>
<tns:GlobalTransportEventCode>Delivery</tns:GlobalTransportEventCode>
</tns:TransportationEvent>
</tns:scheduledEvent>

  • DeliveryLocation

Onetrail XML:

  • To identify the Seller: fromRole
  • To identify the Buyer: toRole
  • Where the goods are shipped to in case of warehouse shipment: ShipTo

Edifact:

  • To identify the Buyer: UNB020, S002, 0004
  • To identify the Seller: UNB020, S002, 0004
  • Where the goods are shipped to in case of Warehouse Shipment: NAD+ST

The planned shipment date is available in the order response messages. The planned shipment date can be "provided" and / or "calculated" in the order response.

The provided shipment date is mandatory, while the calculated shipment date is optional in the order response.

Several scheduled events are available. The following options are supported:

  • Ship
  • Ship Calculated
  • Delivery
  • Delivery Calculated
Info

for UBL, only delivery dates are supported


UBL XML:

Code Block
languagexml
titleDelivery element
<cac:Delivery>
	<cac:PromisedDeliveryPeriod>
		<cbc:StartDate>2024-12-06</cbc:StartDate>
		<cbc:EndDate>2024-12-06</cbc:EndDate>
	</cac:PromisedDeliveryPeriod>
</cac:Delivery>


Onetrail XML:

Code Block
languagexml
titleScheduled event element
<tns:scheduledEvent>
	<tns:TransportationEvent>
		<tns:DateStamp>20140307T000000</tns:DateStamp>
		<tns:GlobalTransportEventCode>Ship</tns:GlobalTransportEventCode>
	</tns:TransportationEvent>
</tns:scheduledEvent>
<tns:scheduledEvent>
	<tns:TransportationEvent>
		<tns:DateStamp>201403010T000000</tns:DateStamp>
		<tns:GlobalTransportEventCode>Delivery</tns:GlobalTransportEventCode>
	</tns:TransportationEvent>
</tns:scheduledEvent>

Format & Syntax


UBL XML

The format of the UBL

Format & Syntax

The format of the standard Onetrail XML messages is XML version 1.0. The encoding must be UTF-8. Besides XML, Onetrail also supports a standard Edifact D97 Order Response. 

Info
For more information about the syntax of the order response please refer to: technical documentation order response

EDIFACT

Peppol BIS version 3 - May 2024 Release

Onetrail XML

The format of the Onetrail XML messages is XML version 1.0. The encoding must be UTF-8. 

Info

For more information about the syntax of the order response please refer to: technical documentation order response

EDIFACT

Besides UBL and Onetrail XML, Onetrail also supports a standard Edifact Besides XML Onetrail also supports a standard Edifact D97A ORDRSP besides a lot of other industry standards. For more information about supported standards we refer to: Available Industry Standards

Info
For the EDIFACT documentation please refer to: Edifact order response documentation

Communication

Info

For more information about the supported communication methods, please refer to: communication methods

Examples

Info

Please refer to the examples: Order response



Supported processes by Onetrail

TPN™

TPN in the Order Response Message

In this section we describe the various supported processes in the Order Response Message. The availability of each individual Onetrail TPN™ TPN supported process for each Seller may vary depending on their capabilities as shown in the table Overview Supported Processes Order Response Message. Each process is described in the subsections below. For more information about which Seller supports which process types in the Order Response Message, please contact our TPN Delivery Team by phone at +31 30 697 32 88 or by e-mail TPN.Delivery@Onetrail.com

Time between Order and Order Status Updates

The time between Orders and Order Status (Update) varies per Seller and depends on when the Order Status (Update) Messages are delivered to Onetrail by the Seller.

Generic Information about

Status updates with the Order Response Process

An A status update for the entire Order (on header level) and/or for each order line can be provided by the Seller.
It will give an insight of the current status of the Order at the Seller.

UBL XML

usage

:

This can be defined in the XML element. Possible values on order header level are:

  • 'Accept' (Order is accepted by the seller)
  • 'Reject' (Order is on hold)
  • 'Change' (Order is accepted with modifications)
    • AB: Message acknowledgement
    • AP: Accepted
    • RE: Rejected
    • CA: Conditionally accepted

    Possible values on order line level are:

    • 1: Order line is added
    • 3: Changed
    • 5: Accepted without amendment.
    • 7: Not accepted
    • 9: Deleted
    • 42: Already delivered
    Info

    The action code 9: Deleted, is Onetrail specfic and not a part of the UBL standard yet.

    Onetrail XML:

    'Delete' (Order is deleted)

    Possible values on order line header level are:

    • 'Accept' (Order is accepted by the seller)
    • 'Reject' (Order is on hold)
    • 'Change' (Order is accepted with modifications)
    • 'Delete' (Order is deleted)

    Possible values on order line level are:

    • 'Accept' (Line is accepted without changes)
    • 'Change' (Line is modified by Seller)
    • 'Add' (Line is added by Seller)
    • 'Reject' (Line is on hold)
    • 'Delete' (Line is deleted)

    EDIFACT

    usage

    :

    On header level use the Message function code in the BGM segment for this.
    Possible values on order header level are:

    • '29' (Order is Accepted without amendment by the Seller)
    • '27' (Order is Not Accepted/on hold)
    • '4' (Order is Changed/accepted with modifications)
    • '3' (Order is Deleted)

    On line level use the Action request/notification coded in the LIN segment for this.
    Possible values on order line level are:

    • '5' (Line is accepted without changes)
    • '6' (Line is accepted with changes)
    • '3' (Line is modified by Seller)
    • '1' (Line is added by Seller)
    • '7' (Line is not accepted/on hold)
    • '2' (Line is deleted)

    The usage for these status codes are described further below. As a general response rule, the quantities reported in the and elements combined must be the same value as the ordered quantity.
    Remark:

    Info
    iconfalse
    With one exception, being the MOQ (Minimum Order Quantity) where the order requested might be eleven pieces and scheduled or shipped might be twelve pieces as there are twelve (minimum order quantity or per twelve) in one package.

    Onetrail

    Check

    checks on actual changes

    on Line Level

    in the Order Status Updates

    Some Sellers are not able to inform the Buyer about only the changes on order line level of the Purchase Orderpurchase order.
    Or there are Sellers who send out an update as long as an Order order is not delivered completely.
    Due to this the Buyer is receiving a lot of updates about the Purchase Orderpurchase order, without any significant changes.
    Onetrail is able to check if there are changes on the Order Line Level in the received Order Status Update from the Seller.
    When there is a change Onetrail will send an Order Status Update to the Buyer. If not: Onetrail will block the outbound message to the Buyer.

    Ship Date or ETA

    Sellers use different dates in their Order Status Messages.
    Onetrail you will inform the Buyer about which Seller is sending which dates in the Order Status Messages.
    For instance, the ship date is a mandatory requirement, while the Seller can optionally add a delivery date, such as an estimated time of arrival (ETA), to the Order Status Message.

    Info
    Use of Purchase Order Line Numbers
    For UBL XML it will be always the delivery date,

    Use of purchase order line numbers

    When the Seller is able to add the Purchase Order purchase order line number in their ERP on the received Orders and they can send it back in the Order Response Message, The Buyer can use 'their' Purchase Order purchase order line number on the Order Response Message to match the used line numbers in the Purchase Order.
    This is mostly supported when Orders are placed electronically (via Onetrail TPN™TPN).
    Be aware that not all Sellers are able to store the Purchase Order line numbers in their ERP system!

    Supported Product Codes

    , in such a case, Onetrail will try to align the Order Response with the Purchase Order and add the purchase order line number to the Order Response.

    Supported product codes in the Order Response Message

    Onetrail supports different product codes in the Order Response Message from the Seller:

    • Seller Product Codes: Stock Keeping Unit number (SKU).
    • Manufacturers / Vendor Product Codes: Manufacturer Part Number (MFPN) / Vendor Part Number (VPN).
    • GTIN / EAN Product Codes: Global Trade Item Number (GTIN) / European Article Number (EAN) (a.k.a. International Article Number) a unique product code supplied by GS1.
    • Buyer Product Codes: own product code for Buyers.

    UBL XML

    usage

    :

    ProductIdentification/PartnerProductIdentification/GlobalPartnerClassificationCode = "Seller" , "Manufacturer", "Ean" or "Buyer".

    <PartnerProductIdentification>
         <GlobalPartnerClassificationCode>Manufacturer</GlobalPartnerClassificationCode>
         <ProprietaryProductIdentifier>20E2000CMH</ProprietaryProductIdentifier>
    </PartnerProductIdentification>

    EDIFACT usage:

    Include:
    On line level use Segment 26: LIN
    Item number type coded: SA
    Example: LIN+1+5+BDPS3700B:SA'

    Include:
    On line level use Segment 26: PIA
    Item number type coded: MF
    Item number type coded: EN
    Item number type coded: BP
    Example:
    PIA+1+6655443322:MF'
    PIA+1+4548736013568:EN'
    PIA+1+123456:BP'

    Important Scenario examples and date usage

    Tip

    Scenario Examples:

    Table of Contents
    maxLevel3
    minLevel2
    exclude.*Process|.*Content|.*Choreography|.*Process management|.*Order Status scenarios|.*Format & Syntax|.*Format|.*Communication|.*Examples|.*Introduction|.*Time between Order and Order Status Updates|.*Onetrail Check on actual changes on Line Level in the Order Status Updates|.*Ship Date or ETA|.*Use of Purchase Order Line Numbers|.*Supported Product Codes in the Order Response Message

    Please note that the examples/snippets as shown below are copied directly from the Onetrail XML or Edifact messages.

    Info

    Documentation is available for XSDEdifact D96a and Edifact D97a.

    If you want to validate your XML test messages against the XSD, please use the TPN Portal functionality to easily facilitate this.
    Our TPN Delivery department can provide you on request with access in our TPN Portal and provide further directions on how to Validate the XML messages against the ORDRSP XSD.

    Info

    More information about the XSD or Edifact MIG Documentation can be found here.

    Scenario 1: Order Confirmed without changes

    Products can be delivered at the requested delivery date for the given price.

    • Result:

    Order header Status = Accept
    Order line Status = Accept

     XML usage:

    - Header

    <GlobalPurchaseOrderStatusCode>Accept</GlobalPurchaseOrderStatusCode>
        <requestedEvent>
            <TransportationEvent>
                  <DateStamp>20190429T000000</DateStamp>
                  <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
           <TransportationEvent>
                <DateStamp>20190429T000000</DateStamp>
                <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </scheduledEvent>

     

    - Order Line 1

    <GlobalPurchaseOrderStatusCode>Accept</GlobalPurchaseOrderStatusCode>
        <requestedQuantity>
              <ProductQuantity>200</ProductQuantity>
        </requestedQuantity>
        <scheduledShipQuantity>
              <ProductQuantity>200</ProductQuantity>
        </scheduledShipQuantity>
        <requestedEvent>
             <TransportationEvent>
                  <DateStamp>20190429T000000</DateStamp>
                  <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
             </TransportationEvent>
        </requestedEvent>
        <scheduledEvent>
            <TransportationEvent>
                 <DateStamp>20190429T000000</DateStamp>
                 <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
            </TransportationEvent>
        </scheduledEvent>
        <shippedQuantity>
              <ProductQuantity>0</ProductQuantity>
        </shippedQuantity>
        <totalLineItemAmount>
             <FinancialAmount>
                 <MonetaryAmount>2400.00</MonetaryAmount>
             </FinancialAmount>
        </totalLineItemAmount>
        <unitPrice>
           <FinancialAmount>
               <MonetaryAmount>12.00</MonetaryAmount>
           </FinancialAmount>
       </unitPrice>

    Code Block
    languagexml
    titleItem element
    <cac:Item>
    	<cbc:Name>Canon 719 - Black - original - toner cartridge - for i-SENSYS LBP251, LBP252, LBP253, LBP6310, MF411, MF416, MF418, MF419, MF6140, MF6180</cbc:Name>
    	<cac:SellersItemIdentification>
    		<cbc:ID>SKUB002</cbc:ID>
    	</cac:SellersItemIdentification>
    	<cac:ManufacturersItemIdentification>
    		<cbc:ID>3479B002</cbc:ID>
    	</cac:ManufacturersItemIdentification>
    	<cac:StandardItemIdentification>
    		<cbc:ID schemeID="0160">4960999650289</cbc:ID>
    	</cac:StandardItemIdentification>
    </cac:Item>

    Onetrail XML:

    ProductIdentification/PartnerProductIdentification/GlobalPartnerClassificationCode = "Seller" , "Manufacturer", "Ean" or "Buyer".


    Code Block
    languagexml
    titleProductIdentification element
    <PartnerProductIdentification>
         <GlobalPartnerClassificationCode>Manufacturer</GlobalPartnerClassificationCode>
         <ProprietaryProductIdentifier>20E2000CMH</ProprietaryProductIdentifier>
    </PartnerProductIdentification>

    EDIFACT:

    Include:
    On line level use Segment 26: LIN
    Item number type coded: SA
    Example: LIN+1+5+BDPS3700B:SA'

    Include:
    On line level use Segment 26: PIA
    Item number type coded: MF
    Item number type coded: EN
    Item number type coded: BP
    Example:
    PIA+1+6655443322:MF'
    PIA+1+4548736013568:EN'
    PIA+1+123456:BP'

    Scenario examples and date usage

    Tip

    Scenario Examples:

    Table of Contents
    maxLevel3
    minLevel2
    exclude.*Process|.*Content|.*Choreography|.*Process management|.*Order Status scenarios|.*Format & Syntax|.*Format|.*Communication|.*Examples|.*Introduction|.*Time between Order and Order Status Updates|.*Onetrail checks on actual changes in the Order Status Updates|.*Ship Date or ETA|.*Use of purchase order line numbers|.*Supported product codes in the Order Response Message

    Scenario 1: Order confirmed without changes

    Products can be delivered at the requested delivery date for the given price.

    Statuses:

    • Order header Status = Accept
    • Order line Status = Accept

    UBL XML usage:

    Code Block
    titleOrder header
    <cbc:OrderResponseCode>AP</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleAll order lines
    <cbc:LineStatusCode>5</cbc:LineStatusCode>

    Onetrail XML:

    Code Block
    languagexml
    titleOrder header
    <GlobalPurchaseOrderStatusCode>Accept</GlobalPurchaseOrderStatusCode>


    Code Block
    languagexml
    titleAll order lines
    <GlobalPurchaseOrderStatusCode>Accept</GlobalPurchaseOrderStatusCode>

    EDIFACT:

    Code Block
    titleOrder header
     

    EDIFACT usage:

    - Header
    BGM+231+0420360072+29'
    - Order Line 1


    Code Block
    titleAll order lines
    LIN+1+5+BDPS3700B:SA'
    QTY+21:5:EA'
    QTY+187:5:EA'
    DTM+2:20170920:102'
    DTM+76:20170920:102'
    MOA+146:81.90'
    MOA+203:409.50'
    PRI+AAA:81.9'Scenario

    Scenario 2: Order

    Confirmed

    confirmed with changes

    Products can't be delivered at the requested delivery date and/or for the given requested price.

    Result

    Statuses:

    • Order header Status = Change
    • Order line Status = Change

    UBL XML

    usage

    :

     

    - Header

    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
              <DateStamp>20160930T1500000</DateStamp>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20161003T1500000</DateStamp>
          </TransportationEvent>
       </scheduledEvent>

    - Order Line 1

    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>200</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20160930T1500000</DateStamp>
           </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20161003T1500000</DateStamp>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>
       <totalLineItemAmount>
          <FinancialAmount>
             <MonetaryAmount>2800.00</MonetaryAmount>
          </FinancialAmount>
       </totalLineItemAmount>
       <unitPrice>
          <FinancialAmount>
             <MonetaryAmount>14.00</MonetaryAmount>
          </FinancialAmount>
      </unitPrice>

    Code Block
    titleOrder header
    <cbc:OrderResponseCode>CA</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleOrder line 1
    <cbc:LineStatusCode>3</cbc:LineStatusCode>


    Onetrail XML: 

    Code Block
    languagexml
    titleOrder header
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>


    Code Block
    languagexml
    titleOrder line 1
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>

    EDIFACT:

    Code Block
    titleOrder header
    BGM+231+0420360072+4'


    Code Block
    titleOrder line 1
    LIN+1+6+BDPS3700B:SA'

    Scenario 3: Order on-hold

    When there are price differences, delivery date check with manufacturer is needed, sales block on order, credit check is done, stock differences, products are canceled for sales, etc. the order can be On-Hold for a while.

    Statuses:

    • Order header Status = Reject
    • Order line Status = Reject

    UBL XML:

    Code Block
    languagexml
    titleHeader
    <cbc:OrderResponseCode>RE</cbc:OrderResponseCode>
    <cbc:NoteFinance block</cbc:Note>


    Code Block
    languagexml
    titleAll order lines
    <cbc:Note>Finance block</cbc:Note>
    <cbc:LineStatusCode>7</cbc:LineStatusCode>

    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <remarks>
       <remark context="RejectReason">Finance block</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>


    Code Block
    languagexml
    titleAll order lines
    <remarks>
    
    <remark context="RejectReason">Finance block</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>

    EDIFACT:

    Code Block
    titleHeader
    BGM+231+0420360072+27'
    FTX+ZZZ+one or more lines on hold'


    Code Block
    titleAll order lines
    LIN+1+7+BDPS3700B:SA'
    FTX+ZZZ+line on hold-finance block'

    Scenario 4: Order-line on-hold

    Instead of the whole Order is put On-Hold, only one or more lines can be On-Hold

    Statuses:

    • Order header Status = Change
    • Order line Status = Reject

    UBL XML:

    Code Block
    languagexml
    titleHeader
    <cbc:OrderResponseCode>RE</cbc:OrderResponseCode>
    <cbc:Note>Delivery block for one or more lines</cbc:Note>


    Code Block
    languagexml
    titleLine 1
    <cbc:Note>Customer Services Delivery block</cbc:Note>
    <cbc:LineStatusCode>7</cbc:LineStatusCode>

    Onetrail XML: 

    Code Block
    languagexml
    titleHeader
    <remarks>
       <remark context="RejectReason">Delivery block for one or more lines</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>


    Code Block
    languagexml
    titleOrder line 1
    <remarks>
        <remark context="RejectReason">Customer Services Delivery block</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode> 

    The other order lines are still expected to be delivered and/or are placed in back order.

    EDIFACT:

    EDIFACT usage:

    - Header
    BGM+231+0420360072+4'
    - Order Line 1
    LIN+1+6+BDPS3700B:SA'
    QTY+21:5:EA'
    QTY+187:5:EA' or QTY+83:5:EA'
    DTM+2:20170920:102'
    DTM+76:20170921:102'
    MOA+146:81.90'
    MOA+203:409.50'
    PRI+AAA:81.9'

    Scenario 3: Order on-hold

    When there are price differences, delivery date check with manufacturer is needed, sales block on order, credit check is done, stock availability in warehouse needs extra checking because of physical difference vs ERP, products are stopped for sale (technical issue), etc. the order can be On-Hold.

    • Result:

    Order header Status = Reject
    Order line Status = Reject

    XML usage:

    - Header

    <remarks>
       <remark context="RejectReason">Finance block</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
           <TransportationEvent>
              <DateStamp>20440404T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>

    - Order Line 1

    <remarks>
    <remark context="RejectReason">Finance block</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>200</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
         </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    EDIFACT usage:

    -
    Code Block
    title
    Header
    BGM+231+0420360072+
    27'
    DTM+2:20170920:102'
    DTM+17:20440404:102'
    4'
    FTX+ZZZ+one or more lines on hold'
    


    Code Block
    title
    -
    Order
    Line
    line 1
    LIN+1+7+BDPS3700B:SA'

    QTY+21:5:EA'
    QTY+187:5:EA'
    DTM+2:20170920:102'
    DTM+76:20440404:102'
    MOA+146:81.90'
    MOA+203:409.50'
    
    FTX+ZZZ+line on hold-
    finance
    CS delivery block'

    PRI+AAA:81.9'
    
    

    The other order LIN segments are still expected to be delivered and/or are placed in back order.

    Scenario 5: Order deleted

    When the order isn't accepted (anymore) for Sales reasons or on request of the Buyer the order can be deleted.

    Statuses

    Scenario 4: Order-line on-hold

    Instead of the whole Order is put On-Hold, only one or more lines can be On-Hold

    Result

    :

    • Order header Status =
    Change
    • Delete
    • Order line Status =
    Reject
    • Delete

    UBL XML

    usage

    :

     

    - Header
    Code Block

    <remarks>
       <remark context="RejectReason">Delivery block for one or more lines</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
      </scheduledEvent>

    - Order Line 1

     

    <remarks>
        <remark context="RejectReason">Customer Services Delivery block</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>
        <requestedQuantity>
           <ProductQuantity>200</ProductQuantity>
        </requestedQuantity>
        <scheduledShipQuantity>
           <ProductQuantity>200</ProductQuantity>
        </scheduledShipQuantity>
        <requestedEvent>
           <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
        </requestedEvent>
        <scheduledEvent>
           <TransportationEvent>
              <DateStamp>20440404T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
        </scheduledEvent>
        <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
        </shippedQuantity>

    titleHeader
    <cbc:OrderResponseCode>DE</cbc:OrderResponseCode>
    <cbc:Note>Canceled on customer request</cbc:Note>


    Info
    titleRemark
    The OrderResponseCode DE is not a standard code from the UNCL4343 subset, but added by Onetrail specifically for this scenario.

    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <remarks>
       <remark context="DeleteReason">Canceled on customer request</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode> 


    Code Block
    languagexml
    titleAll order lines
    <remarks>
    <remark context="DeleteReason">Canceled on customer request</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode> 
    

    EDIFACT:

    Code Block
    titleHeader
    BGM+231+0420360072+3'
    FTX+ZZZ+order deleted'
    


    Code Block
    titleAll order lines
    LIN+1+2+BDPS3700B:SA'
    FTX+ZZZ+line deleted-canceled by customer'
    

    Scenario 6: Order line(s) deleted

    When an order line isn't accepted (anymore) for sales reasons or on request of the Buyer one or more order line(s) can be deleted.

    Statuses:

    • Order header Status = Change
    • Order line Status = Delete

    UBL XML:

    Code Block
    languagexml
    titleHeader
    <cbc:OrderResponseCode>CA</cbc:OrderResponseCode>
    <cbc:Note>One or more lines cancelled</cbc:Note>


    Code Block
    languagexml
    titleLine 1
    <cbc:Note>Product is End of Life</cbc:Note>
    <cbc:LineStatusCode>9</cbc:LineStatusCode>


    Info
    titleRemark
    The LineStatusCode 9 is not a standard code from the UNCL1229 subset, but added by Onetrail specifically for this scenario.

    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <remarks>
       <remark context="DeleteReason">One or more lines cancelled</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode> 


    Code Block
    languagexml
    titleOrder line 1
    <remarks>
       <remark context="DeleteReason">Product is End of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode> 


    The other order lines are still expected to be delivered and/or are placed in back order.

    EDIFACT:

    Code Block
    titleHeader
    BGM+231+0420360072+4'
    FTX+ZZZ+one or more lines canceled'
    


    Code Block
    titleOrder line 1
    LIN+1+2+BDPS3700B:SA'
    FTX+ZZZ+line deleted-Product EOL'
    

    The other order LIN segments are still expected to be delivered and/or are placed in back order.

    Scenario 7: Order-line is added

    An extra product can be added to the order like a promotional product or a substitute product (deleted line and new one added).

    Statuses:

    • Order header Status = Change
    • Order line Status = Add

    UBL XML:

    Code Block
    languagexml
    titleHeader
    <cbc:OrderResponseCode>CA</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleLine 1
    <cbc:LineStatusCode>1</cbc:LineStatusCode>

    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>


    Code Block
    languagexml
    titleOrder line 1
    <GlobalPurchaseOrderStatusCode>Add</GlobalPurchaseOrderStatusCode>

    EDIFACT:

    Code Block
    titleHeader
    BGM+231+0420360072+4'


    Code Block
    titleOrder line 1
    LIN+1+1+BDPS3700B:SA'


    Scenario 8: Order-line is split

    UBL XML

    When the order will be partially delivered, the quantity which is available for delivery will be shipped immediately and the quantity which is not available will be put in back-order.

    The Seller reports back to the Buyer if the remaining quantity can be delivered for the same price, another date or not at all.
    In this case, the Seller order response contains a split order line scenario for the original ordered goods.
    The first part of the order line gets status Change.
    The quantity which can be delivered (less then ordered) needs to be put into Quantity.
    The second part of the Buyer order line will either get status Change, Reject or Delete depending on the split reason:

    • Use Change only if the price(s) and/or delivery date(s) deviates from the first split order line.
    • Use status Reject (On Hold) instead in case there is a technical, financial or stock issue with the delivery of the remaining quantity;
    • Use Delete if the remaining quantity will not be delivered;
    Info
    In case of an unknown delivery date, use the 'Unknown' date 04-04-2044 to indicate an unknown delivery date. As soon as a delivery date is available, send the new delivery date with the same status Change, in the next OrdRsp message.

    Onetrail XML

    When the order will be partially delivered, the quantity which is available for delivery will be shipped immediately and the quantity which is not available will be put in back-order.

    The Seller reports back to the Buyer if the remaining quantity can be delivered for the same price, another date or not at all.
    In this case, the Seller order response contains a split order line scenario for the original ordered goods.
    The first part of the order line gets status Change.
    The quantity which can be delivered (less then ordered) needs to be put into scheduledShipQuantity.
    The second part of the Buyer order line will either get status Change, Reject or Delete depending on the split reason:

    • Use Change only if the price(s) and/or delivery date(s) deviates from the first split order line.
    • Use status Not accepted (On Hold) instead in case there is a technical, financial or stock issue with the delivery of the remaining quantity;
    • Use Delete if the remaining quantity will not be delivered;
    Info
    In case of an unknown delivery date, use the 'Unknown' date 04-04-2044 to indicate an unknown delivery date. As soon as a delivery date is available, send the new delivery date with the same status Change, in the next OrdRsp message.


    For every possible scenario, the remaining quantity which is not equal to the ordered quantity, must be specified in the ScheduledShipQuantity. The total of all ScheduledShipQuantity mentioned in each split line, must be equal to the original OrderedQuantity when added up together.

    Statuses

    The other order lines are still expected to be delivered and/or are placed in back order.

    EDIFACT usage:

    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    FTX+ZZZ+one or more lines on hold'
    - Order Line 1
    LIN+1+7+BDPS3700B:SA'
    QTY+21:5:EA'
    QTY+187:5:EA'
    DTM+2:20170920:102'
    DTM+76:20440404:102'
    MOA+146:81.90'
    MOA+203:409.50'
    FTX+ZZZ
    +line on hold-CS delivery block'
    PRI+AAA:81.9'

    The other order LIN segments are still expected to be delivered and/or are placed in back order.

    Scenario 5: Order Deleted

    When the order isn't accepted (anymore) for Sales reasons or on request of the Buyer the order can be deleted.

    • Result:

    Order header Status = Delete
    Order line Status = Delete

    XML usage:

    - Header

    <remarks>
       <remark context="DeleteReason">Canceled on customer request</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>

    - Order Line 1

    <remarks>
    <remark context="DeleteReason">Canceled on customer request</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
    <requestedQuantity>
    <ProductQuantity>200</ProductQuantity>
    </requestedQuantity>
    <scheduledShipQuantity>
    <ProductQuantity>200</ProductQuantity>
    </scheduledShipQuantity>
    <requestedEvent>
    <TransportationEvent>
    <DateStamp>20190429T000000</DateStamp>
    <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
    </TransportationEvent>
    </requestedEvent>
    <scheduledEvent>
    <TransportationEvent>
    <DateStamp>20440404T000000</DateStamp>
    <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
    </TransportationEvent>
    </scheduledEvent>
    <shippedQuantity>
    <ProductQuantity>0</ProductQuantity>
    </shippedQuantity>

    EDIFACT usage:

    - Header
    BGM+231+0420360072+3'
    DTM+2:20170920:102'
    DTM+17:20440404:102'
    FTX+ZZZ+order deleted'
    - Order Line 1
    LIN+1+2+BDPS3700B:SA'
    QTY+21:5:EA'
    QTY+182:5:EA'
    DTM+2:20170920:102'
    DTM+76:20440404:102'
    MOA+146:81.90'
    MOA+203:409.50'
    FTX+ZZZ
    +line deleted-canceled by customer'
    PRI+AAA:81.9'

    Scenario 6: Order Line(s) Deleted

    When an Order Line isn't accepted (anymore) for Sales reasons or on request of the Buyer one or more Order Line(s) can be deleted.

    • Result:

    Order header Status = Change
    Order line Status = Delete

    XML usage:
    - Header

    <remarks>
       <remark context="DeleteReason">One or more lines canceled</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
         </TransportationEvent>
      </scheduledEvent>

    - Order Line 1

    <remarks>
       <remark context="DeleteReason">Product is End of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>200</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

     

    The other order lines are still expected to be delivered and/or are placed in back order.

    EDIFACT usage:

    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    FTX+ZZZ+one or more lines canceled'
    - Order Line 1
    LIN+1+2+BDPS3700B:SA'
    QTY+21:5:EA'
    QTY+182:5:EA'
    DTM+2:20170920:102'
    DTM+76:20440404:102'
    MOA+146:81.90'
    MOA+203:409.50'
    FTX+ZZZ
    +line deleted-Product EOL'
    PRI+AAA:81.9'

    The other order LIN segments are still expected to be delivered and/or are placed in back order.

    Scenario 7: Order-line is added

    An extra product can be added to the Order like a promotional Product or a substitute Product (Deleted Line and new one added).

    Result

    :

    • Order header Status = Change
    • Order line Status =
    AddXML usage:
    - Header

    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>

    - Order Line 1

    <buyerLineItem/>
    <GlobalPurchaseOrderStatusCode>Add</GlobalPurchaseOrderStatusCode>
       <requestedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>200</ProductQuantity>
       </scheduledShipQuantity>
       <ProductIdentification>
          <GlobalProductIdentifier>20E2000CMH</GlobalProductIdentifier>
          <PartnerProductIdentification>
              <GlobalPartnerClassificationCode>Manufacturer</GlobalPartnerClassificationCode>
              <ProprietaryProductIdentifier>20E2000CMH</ProprietaryProductIdentifier>
          </PartnerProductIdentification>
          <PartnerProductIdentification>
              <GlobalPartnerClassificationCode>Seller</GlobalPartnerClassificationCode>
              <ProprietaryProductIdentifier>SellerPN1</ProprietaryProductIdentifier>
          </PartnerProductIdentification>
          <PartnerProductIdentification>
             <GlobalPartnerClassificationCode>Buyer</GlobalPartnerClassificationCode>
             <ProprietaryProductIdentifier>BuyerPN1</ProprietaryProductIdentifier>
          </PartnerProductIdentification>
          <PartnerProductIdentification>
             <GlobalPartnerClassificationCode>EAN</GlobalPartnerClassificationCode>
             <ProprietaryProductIdentifier>8712345678921</ProprietaryProductIdentifier>
          </PartnerProductIdentification>
       </ProductIdentification>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
      </shippedQuantity>

    EDIFACT usage:

    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    - Order Line 1
    LIN+1+1+BDPS3700B:SA'
    QTY+21:0:EA'
    QTY+187:5:EA'
    DTM+2:20170920:102'
    DTM+76:20170920:102'
    MOA+146:81.90'
    MOA+203:409.50'
    PRI+AAA:81.9'
    RFF+LI:'

    Scenario 8: Order-line is split

    XML usage:

    When the Order will be partially delivered, the quantity which is available for delivery will be shipped immediately and the quantity which is not available will be put in back-order.
    The Seller reports back to the Buyer if the remaining quantity can be delivered for the same price, same date or even at all.
    In this case the Seller Order Response contains a split Buyer order line scenario for the original ordered goods.
    The first part of the Buyer order line gets status Change.
    The quantity which can be delivered (less then ordered) needs to be put into scheduledShipQuantity.
    The second part of the Buyer order line will either get status Change, Reject or Delete depending on the split reason:

    • Use Change only if the price(s) and/or delivery date(s) deviates from the first split order line.

    In case of an unknown delivery date, use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate an unknown Delivery Date.

    • Use status Reject (On Hold) instead in case there is a technical, financial or stock issue with the delivery of the remaining quantity;
    • Use Delete if the remaining quantity will not be delivered;

    For every possible scenario, the remaining quantity which is not equal to the ordered quantity, must be specified in the ScheduledShipQuantity. The total of all ScheduledShipQuantity mentioned in each split line, must be equal to the original OrderedQuantity when added up together.

    • Result:

    Order header Status = Change
    Order line Status = Change

    XML usage 8a Split line Change/Backorder

    Remark: Use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate unknown Delivery Date. As soon as a Delivery Date is available, send through the new Delivery Date with the same status Change, in the next OrdRsp message.

    - Header

    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
        <requestedEvent>
           <TransportationEvent>
               <DateStamp>20190429T000000</DateStamp>
               <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
        </requestedEvent>
        <scheduledEvent>
           <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>

    - Order Line 1

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>150</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    - Order Line 2

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
           <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
           <TransportationEvent>
               <DateStamp>20190514T000000</DateStamp>
               <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    XML usage 8b Split line Reject/On-Hold

    - Header

    <remarks>
       <remark context="RejectReason">Rejected:Approval Denied</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>

    - Order Line 1

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>150</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    - Order Line 2

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <remarks>
       <remark context="RejectReason">Rejected:Approval Denied</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
           <TransportationEvent>
               <DateStamp>20190429T000000</DateStamp>
               <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    XML usage 8c Split line Delete/End Of Life(EOL)

    - Header

    <remarks>
       <remark context="DeleteReason">Deleted:Product End Of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
       <requestedEvent>
          <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>

    - Order Line 1

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>150</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
           <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    - Order Line 2

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <remarks>
       <remark context="DeleteReason">Deleted:Product End Of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    Remark: In this scenario, if the Deleted quantity of 50 is communicated after the first quantity of 150 is already shipped, the first of the split lines in the second Order Response can also provide the quantity of 150 as already delivered, by moving it from 'scheduledShipQuantity' to the 'shippedQuantity'.

    - Order Line 1

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>0</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>150</ProductQuantity>
       </shippedQuantity>

    - Order Line 2

    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <remarks>
       <remark context="DeleteReason">Deleted:Product End Of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    EDIFACT usage:

    When the Order will be partially delivered, the quantity which is available for delivery will be shipped immediately and the quantity which is not available will be put in back-order.
    The Seller reports back to the Buyer if the remaining quantity can be delivered for the same price, same date or even at all.
    In this case the Seller Order Response contains a split Buyer order line scenario for the original ordered goods.
    The first part of the Buyer order line gets status Change.
    The quantity which can be delivered (less then ordered) needs to be put into Quantity scheduled (QTY+187).
    The second part of the Buyer order line will either get status Changed (3), Not Accepted (7) or Deleted (2) depending on the split reason:

    • Use Changed (3) only if the price(s) and/or delivery date(s) deviates from the first split order line.

    In case of an unknown delivery date, use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate an unknown Delivery Date.

    • Use status Not Accepted/On-Hold (7) instead in case there is a technical, financial or stock issue with the delivery of the remaining quantity;
    • Use Deleted (2) if the remaining quantity will not be delivered;

    For every possible scenario, the remaining quantity which is not equal to the ordered quantity, must be specified in the Quantity scheduled (QTY+187) or Backorder Quantity (QTY+83). The total of all Quantity scheduled (QTY+187) and Backorder Quantity (QTY+83) and Canceled Quantity (QTY+182) and Supplied Quantity (QTY+169) mentioned in each split line, must be equal to the original Ordered Quantity (QTY+21) when added up together.

    • Result:

    Order header Status = Change
    Order line Status = Change

    Edifact usage 8a Split line Change/Backorder

    Remark: Use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate unknown Delivery Date. As soon as a Delivery Date is available, send through the new Delivery Date with the same status Change, in the next OrdRsp message.

    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    - Order Line 1
    LIN+1+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:6:EA'
    DTM+2:20170920:102'
    DTM+76:20170920:102'
    MOA+146:62.89'
    • Change, Reject or Delete

    EDIFACT

    When the Order will be partially delivered, the quantity which is available for delivery will be shipped immediately and the quantity which is not available will be put in back-order.
    The Seller reports back to the Buyer if the remaining quantity can be delivered for the same price, same date or even at all.
    In this case the Seller Order Response contains a split Buyer order line scenario for the original ordered goods.
    The first part of the Buyer order line gets status Change.
    The quantity which can be delivered (less then ordered) needs to be put into Quantity scheduled (QTY+187).
    The second part of the Buyer order line will either get status Changed (3), Not Accepted (7) or Deleted (2) depending on the split reason:

    • Use Changed (3) only if the price(s) and/or delivery date(s) deviates from the first split order line.

    In case of an unknown delivery date, use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate an unknown Delivery Date.

    • Use status Not Accepted/On-Hold (7) instead in case there is a technical, financial or stock issue with the delivery of the remaining quantity;
    • Use Deleted (2) if the remaining quantity will not be delivered;

    For every possible scenario, the remaining quantity which is not equal to the ordered quantity, must be specified in the Quantity scheduled (QTY+187) or Backorder Quantity (QTY+83). The total of all Quantity scheduled (QTY+187) and Backorder Quantity (QTY+83) and Canceled Quantity (QTY+182) and Supplied Quantity (QTY+169) mentioned in each split line, must be equal to the original Ordered Quantity (QTY+21) when added up together.

    • Statuses:

    Order header Status = Change
    Order line Status = Change

    Scenario 8a: Split line with first line to be delivered and second line in backorder

    UBL XML:

    Code Block
    titleHeader
    <cbc:OrderResponseCode>AP</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleOrder line 1
    <cbc:ID>1</cbc:ID>
    <cbc:LineStatusCode>3</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">150.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2024-12-06</cbc:StartDate>
    		<cbc:EndDate>2024-12-06</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Code Block
    languagexml
    titleOrder line 2
    <cbc:ID>2</cbc:ID>
    <cbc:LineStatusCode>3</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">150.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2024-12-30</cbc:StartDate>
    		<cbc:EndDate>2024-12-30</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    


    Code Block
    languagexml
    titleSplit line 1
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>150</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>


    Code Block
    languagexml
    titleSplit line 2
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
           <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
           <TransportationEvent>
               <DateStamp>20190514T000000</DateStamp>
               <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    EDIFACT

    Info
    titleRemark
    Use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate unknown Delivery Date. As soon as a Delivery Date is available, send through the new Delivery Date with the same status Change, in the next OrdRsp message.


    Code Block
    titleHeader
    BGM+231+0420360072+4'
    D+2:20170920:102'
    D+17:20170920:102'
    - Order Line 1
    LIN+1+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:6:EA'
    D+2:20170920:102'
    D+76:20170920:102'
    MOA+146:62.89'
    MOA+203:377.34'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'


    Code Block
    titleOrder line 2
    LIN+2+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+83:4:EA'
    D+2:20170920:102'
    D+76:20171012:102'
    MOA+146:62.89'
    MOA+203:251.56'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'

    Scenario 8b: Split line with first line to be delivered and second line with status on-hold (reject)

    UBL XML:

    Code Block
    titleHeader
    <cbc:OrderResponseCode>CA</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleOrder line 1
    <cbc:ID>1</cbc:ID>
    <cbc:LineStatusCode>3</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">150.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2024-12-06</cbc:StartDate>
    		<cbc:EndDate>2024-12-06</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Code Block
    languagexml
    titleOrder line 2
    <cbc:ID>2</cbc:ID>
    <cbc:LineStatusCode>7</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">50.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2044-04-04</cbc:StartDate>
    		<cbc:EndDate>2044-04-04</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <remarks>
       <remark context="RejectReason">Rejected:Approval Denied</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>


    Code Block
    languagexml
    titleSplit line 1
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>150</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>


    Code Block
    languagexml
    titleSplit line 2
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <remarks>
       <remark context="RejectReason">Waiting for approval for price change</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Reject</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
           <TransportationEvent>
               <DateStamp>20190429T000000</DateStamp>
               <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    EDIFACT

    Info
    titleRemark
    Use the Onetrail defined generic 'Unknown' date 04-04-2044 to indicate unknown Delivery Date. As soon as a Delivery Date is available, send through the new Delivery Date with the same status Change, in the next OrdRsp message.


    Code Block
    titleHeader
    BGM+231+0420360072+4'
    D+2:20170920:102'
    D+17:20170920:102'
    - Order Line 1
    LIN+1+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:6:EA'
    D+2:20170920:102'
    D+76:20170920:102'
    MOA+146:62.89'
    MOA+203:377.34'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'


    Code Block
    titleOrder line 2
    LIN+2+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+83:4:EA'
    D+2:20170920:102'
    D+76:20171012:102'
    MOA+146:62.89'
    MOA+203:251.56'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'

    Scenario 8c: Split line with first line to be delivered and second line deleted

    UBL XML:

    Code Block
    titleHeader
    <cbc:OrderResponseCode>CA</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleOrder line 1
    <cbc:ID>1</cbc:ID>
    <cbc:LineStatusCode>3</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">150.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2024-12-06</cbc:StartDate>
    		<cbc:EndDate>2024-12-06</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Code Block
    languagexml
    titleOrder line 2
    <cbc:ID>2</cbc:ID>
    <cbc:LineStatusCode>9</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">50.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2044-04-04</cbc:StartDate>
    		<cbc:EndDate>2044-04-04</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Onetrail XML:

    Code Block
    languagexml
    titleHeader
    <remarks>
       <remark context="DeleteReason">Deleted:Product End Of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode> 


    Code Block
    languagexml
    titleSplit line 1
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>150</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
           <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
           </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>


    Code Block
    languagexml
    titleSplit line 2
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <remarks>
       <remark context="DeleteReason">Deleted:Product End Of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
              <DateStamp>20190429T000000</DateStamp>
              <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    EDIFACT

    Code Block
    titleHeader
    BGM+231+0420360072+4'
    D+2:20170920:102'
    D+17:20170920:102'
    FTX+ZZZ+One or more lines canceled'


    Code Block
    titleOrder line 1
    LIN+1+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:6:EA'
    D+2:20170920:102'
    D+76:20170920:102'
    MOA+146:62.89'
    MOA+203:377.34'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'


    Code Block
    titleOrder line 2
    LIN+2+2+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+182:4:EA'
    D+2:20170920:102'
    D+76:20440404:102'
    MOA+146:62.89'
    MOA+203:251.56'
    FTX+ZZZ+line deleted-Product EOL'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'


    Info
    titleRemark
    In this scenario, if the Canceled/Deleted quantity of 4 is communicated after the first quantity of 6 is already shipped, the first of the split lines in the second Order Response can also provide the quantity of 6 as already delivered, by moving it from 'Quantity scheduled' to the 'Supplied quantity'.

    Scenario 8d: Split line with first line already delivered and second line deleted

    Info
    titleRemark
    In this scenario, the second part with quantity of 50 is deleted after the first batch of 150 is already shipped, this will can only happen in a second or later order response, as the first order response  will have the scheduled delivery date,

    UBL XML:

    Code Block
    titleHeader
    <cbc:OrderResponseCode>CA</cbc:OrderResponseCode>


    Code Block
    languagexml
    titleOrder line 1
    <cbc:ID>1</cbc:ID>
    <cbc:LineStatusCode>42</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">150.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2024-12-06</cbc:StartDate>
    		<cbc:EndDate>2024-12-06</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>


    Code Block
    languagexml
    titleOrder line 2
    <cbc:ID>2</cbc:ID>
    <cbc:LineStatusCode>9</cbc:LineStatusCode>
    <cbc:Quantity unitCode="EA" unitCodeListID="UNECERec20">50.00</cbc:Quantity>
    <cac:Delivery>
    	<cac:PromisedDeliveryPeriod>
    		<cbc:StartDate>2044-04-04</cbc:StartDate>
    		<cbc:EndDate>2044-04-04</cbc:EndDate>
    	</cac:PromisedDeliveryPeriod>
    </cac:Delivery>

    Onetrail XML:

    Code Block
    languagexml
    titleSplit line 1
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <GlobalPurchaseOrderStatusCode>Change</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-10</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>0</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
          <ProductQuantity>150</ProductQuantity>
       </shippedQuantity>


    Code Block
    languagexml
    titleSplit line 2
    <buyerLineItem>
       <LineNumber>1</LineNumber>
    </buyerLineItem>
    <remarks>
       <remark context="DeleteReason">Deleted:Product End Of Life</remark>
    </remarks>
    <GlobalPurchaseOrderStatusCode>Delete</GlobalPurchaseOrderStatusCode>
    <LineNumber>10-20</LineNumber>
       <requestedQuantity>
          <ProductQuantity>200</ProductQuantity>
       </requestedQuantity>
       <scheduledShipQuantity>
          <ProductQuantity>50</ProductQuantity>
       </scheduledShipQuantity>
       <requestedEvent>
          <TransportationEvent>
             <DateStamp>20190429T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </requestedEvent>
       <scheduledEvent>
          <TransportationEvent>
             <DateStamp>20440404T000000</DateStamp>
             <GlobalTransportEventCode>Ship</GlobalTransportEventCode>
          </TransportationEvent>
       </scheduledEvent>
       <shippedQuantity>
           <ProductQuantity>0</ProductQuantity>
       </shippedQuantity>

    EDIFACT

    Code Block
    titleHeader
    BGM+231+0420360072+4'
    D+2:20170920:102'
    D+17:20170920:102'
    FTX+ZZZ+One or more lines canceled'


    Code Block
    titleOrder line

    MOA+203:377.34'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'- Order Line 2LIN+2+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+83:4:EA'
    DTM+2:20170920:102'
    DTM+76:20171012:102'
    MOA+146:62.89'
    MOA+203:251.56'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'

    Edifact usage 8b Split line Reject/On-Hold

    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    FTX+ZZZ+Order line blocked-CS block'
    - Order Line 1
    LIN+1+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:6:EA'
    DTM+2:20170920:102'
    DTM+76:20170920:102'
    MOA+146:62.89'
    MOA+203:377.34'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'
    - Order Line 2
    LIN+2+7+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:4:EA'
    DTM+2:20170920:102'
    DTM+76:20440404:102'
    MOA+146:62.89'
    MOA+203:251.56'
    FTX+ZZZ
    +Order line blocked-CS block'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'

    Edifact usage 8c Split line Delete/End Of Life(EOL)

    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    FTX+ZZZ+One or more lines canceled'
    - Order Line 1
    LIN+1+3+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+187:6:EA'
    DTM+2:20170920:102'
    DTM+76:20170920:102'
    MOA+146:62.89'
    MOA+203:377.34'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'
    - Order Line 2
    LIN+2+2+BDPS3700B:SA'
    QTY+21:10:EA'
    QTY+182:4:EA'
    DTM+2:20170920:102'
    DTM+76:20440404:102'
    MOA+146:62.89'
    MOA+203:251.56'
    FTX+ZZZ
    +line deleted-Product EOL'
    PRI+AAA:62.89'
    RFF+VN:11223344:001'
    RFF+LI:1'
    Remark: In this scenario, if the Canceled/Deleted quantity of 4 is communicated after the first quantity of 6 is already shipped, the first of the split lines in the second Order Response can also provide the quantity of 6 as already delivered, by moving it from 'Quantity scheduled' to the 'Supplied quantity'.
    - Header
    BGM+231+0420360072+4'
    DTM+2:20170920:102'
    DTM+17:20170920:102'
    FTX+ZZZ+One or more lines canceled'
    - Order Line
    1
    LIN+1+3+BDPS3700B:SA'

    
    QTY+21:10:EA'

    
    QTY+169:6:EA'

    DTM
    
    D+2:20170920:102'

    DTM
    
    D+76:20170920:102'

    
    MOA+146:62.89'

    
    MOA+203:377.34'

    
    PRI+AAA:62.89'

    
    RFF+VN:11223344:001'

    
    RFF+LI:1'


    Code Block
    title
    -
    Order
    Line
    line 2
    LIN+2+2+BDPS3700B:SA'

    
    QTY+21:10:EA'

    
    QTY+182:4:EA'

    DTM
    
    D+2:20170920:102'

    DTM
    
    D+76:20440404:102'

    
    MOA+146:62.89'

    
    MOA+203:251.56'

    
    FTX+ZZZ+line deleted-Product EOL'

    
    PRI+AAA:62.89'

    
    RFF+VN:11223344:001'

    
    RFF+LI:1'

    Dates: explanation on how to use the different Delivery and Shipment Dates

    Within the Onetrail message format, scheduled events with different date types can be provided by the Sellers indicating the different types of events. Sellers can provide the day and time a shipment leaves the Sellers warehouse. An ultimate date of delivery can be indicated by either earliest or latest delivery date. A Seller can use one of the following enumerations for the element ‘GlobalTransportEventCode’ inside the ‘scheduledEventType’:

    • 'Ship' (When the goods leave the Seller's warehouse)
    • 'EarliestDelivery' (1st day of the delivery period / window at the Buyer’s warehouse)
    • 'LatestDelivery' (Last day of the delivery period / window at the Buyer’s warehouse)


    ...